Please see table below for the Focus Schedule columns, along with its Data Format.
Asterisks (*) indicate required fields.
Focus Schedule Columns | Data Format/ Accepted Values |
ID* | Numeric value Must be unique |
WBS* | Numeric value (Ex. 1) Must be unique |
Title* | 500 characters max |
Percent Complete* | Percentage value |
Start Date* | Date should be within Project Start Date and Project End Date.
|
End Date* | Date should be within Project Start Date and Project End Date.
|
Predecessor / Successor | x:n (line ID : dependency code) Must be an ID within the file |
Participants / Assigned Resources | Must be assigned user in the Project (Firstname Lastname) |
Mark as Project Milestone | Yes or No |
Mark as Portfolio Milestone | Yes or No |
Mark as Activity | Yes or No |
Mark as Deliverable | Yes or No |
Project Phase | Project Phases outlined within Project Settings (only if marked as deliverable, default is Overall Project) |
Manually Scheduled | Yes or No |
| Workstream | Workstreams outlined within Project Settings (default is Overall Project) |